Carried out measures in the line of much more increasing of exploitation level is continued in "Absheron Regional Electric Network". It is reported that the information received from the network, measures mainly include substations and transmission lines. Given the beginning of the work done in the past year, the work plan for the current year is done.

According to the information given by mentioned enterprise to the Press – release of "Azerenergy" JSC, 220 kV  "Sangachal s/s" oil circuit breakers, current transformers and other equipment have been replaced by new ones. This is due to the connection of new substation technical capacity there. Deep Water Jacket Plant named after Heydar Aliyev, in this example, the  plant and "Khojahasan" is a substation . Currently , 110 kV reconstruction work continues " Sangachal".

At the same time , "Puta" S acted in reconstruction. Here, the existing capacity of 40 MVA to 63 MVA increased with one change . This is due to the compound of a new substation . It should be noted that "Ahmedli" structure substation ORU previously used to increase the level of fat in the restoration work underway to replace the circuit breakers. " 8 - km " The reconstruction of 110 kV , 10 kV distribution pattern continues. By the way, peninsula, characterized by a particular role in the power supply Peninsula 110 kV "Dubendi" complete reconstruction of the 110 kV substation is planned . Work is being done to increase the capacity of transformers, circuit breakers and oil circuit breakers include the replacement. "Surahani"   actions are carried out in the direction of modernization of the operating equipment .

Modern type 220 ​​kV "Zabrat", than last year 220 kV substation was commissioned in the source said earlier this year at its 110 kV 180 MVA each switch is connected to an input circuit 2 transformers. Furthermore, the output of existing lines connected to lines 110 kV. This  in turn, system important  " Excavation " or  s/s about half led to a reduction in the burden .

220 kV " Boyuk Shor " substation is under construction. Analogies will be chosen between the specificity of the substation. So all these substations connected power plants and substations . Thus, the stability of  power even stronger. It should be noted that this substation capacity of 250 MW already installed and finishing work is carried out from three autotransformers . Substation will be built in the near future , the new plant will increase its technical capabilities . At the same time , the bulk of realized project, which provides power to "Khirdalan"  there of Baku in the future will lead to a significant reduction .