REPAIR WORK IS CONTINUED
Supplying of technical indicators in much more regular form, carrying out of capital and maintenance repair work, decreasing of losses at “Shirvan Regional Electric Network” (REN) are the main orders standing in front of power engineering specialists of this enterprise.
According to the information given by “Hajigabul Electric Network” (EN) to the Press – release of “Azerenergy” JSC, about 1,3 km cable line was installed and about 6,5 km line was repaired in order to increase quality and regularity of electric power of the consumers of the enterprise service territory.
Lets` noted that, two transformer points (TP) were constructed, 91 TP were repaired in the line of reconstruction work. At the same time, 11 transformers by 2,33 MVA were capital repaired.
Under the information given by “Neftchala” EN, different setting repair work were implemented at about 50 km part of the lines by 10, 6 and 0,4 kV in the line of carried out reconstruction and repair work.
Lets` also noted that, these type of repair work were implemented at TP belonging to mentioned enterprise. So that, more than 140 TP were repaired, 20 transformers by 3,5 MVA were capital repaired and put into operation.
It should be noted that, reconstruction work and repair work were continued at TL and TP of mentioned EN belonging to the balance as at other EN.