Different type repair – restoration and reconstrcution work were carried out in order to supply the consumers of Shabron and Siyazan regionas of Khachmaz regional electric network with electric power during the I quarter of the current year.
So that, 2 outdated oil circuit breakers were substituted with new vacuum breakers at Shabran s/s by 110/35/10 kV by Shabron region electric network specialists, by the way, maintenance repair work was implemenetd at 15 transformer points by 10/6-0,4 kV, transformer oil was added to the transformers.
Capital repair work was implemenetd at 1,49 km distance of Dagh – biliji, Teleoturuju, Gendab, Demir yol TL by 10 kV and 3,99 km distance of TL by 0,4 kV at Bash Emirkhanli, Khelilli, Devechi villages. 91 stands by 6 kV, 240 ones by 0,4 kV, 273 SHS – 10 market insulars were constructed, 13,6 km AS – 40 marked conductor, 12,9 km distance SIL type cable were installed, 2 s/s at Kilvar village and 1 s/s at Zeyne village was constructed by Azenco JSC. Relevant repair and recosntruction work were implemented at Shabran region.
At the same time, 21,36 km distance of Daghqushchu, Chingil zavod, TL by 10 kV, BSU – 9, Aghbash, Saghlojar, Zarat TL by 6 kVwere maintenance repaired by the specialists of the networks in order to supply the consumers with quality and regular electric power of the consumers of Siyazan region. In general, 30,42 km distance kV of TL by 0,4 kV was maintenance repaired, 0,5 km distance was capital repaired, 2,1 km AS-50 marked conductor was substituted with new one at differenr territories of the region. Totally 11 CTY were capital and maintenance repaired at Siyazan city.
Repair work will be continued in the future in order to decrease accident opening situations and supplying with quality and without interval electric power of the consumers at both regions.