REPAIR – INSPECTION WORK WAS ALSO IMPLEMENTED AT “SHIMAL” PP

Image

Relevant measures plan was prepared and put into operation for stabile and economically work regime of main and subsidiary equipments at Shimal” PP which is the most important generation power at “Absheron” s/s and put into operation under leadership of great leader during independence period.  As  a result of it, technical economical indicators were high during 4 months of the current year. Electric power production was more than 1,3 million kWh than predicted during mentioned period. The power plant is operated in normal work regime under the dispatch graphic.

According to the information given by the power plant to the press – release of “Azerenergy” JSC, 181,3 million kWh electric power was produced in April of the current year and it is 300 thousand more than predicted.

Lets` noted that, 782,3 million kWh electric power was produced against 781 million kWh during 4 months of the current year.

As a result of carried out purposeful measures in the line of increasing of work liability of the equipments, rising of stabile work and exploitation level of energy transmission and distribution systems, high results were achieved at other technical  indicators.

Under other information given by the  source, relevant measures plan was carried out at the enterprise in accordance to available climate condition. Corresponding measures were implemented at the switch yard by 110 kV located at the territory. At the same time, fire extinguisher pumps were repaired and inspected.

It should be noted that, coolers of water system of close circulation was substituted with new one, pump number B was renewed, high pressured pumps were repaired and different setting repair work were operated at other  equipments. At the same time, restoration and greening work was implemented at the territory.

Lets` also noted at the end that, measures plan was operated in accordance to work graphic. Carried out planned repair work makes opportunity for much more improving of technical situation and increasing of  technical economical indicators.

Construction of the second energy block by 409 MW is continued at “Shimal” PP LLC.  After put into operation of the second energy block, the power of PP will be twice increased and will be carried  to 809 MW.